BASOCHU HYDRO POWER PROJECT

WANGDUEPHODRANG

 

Updated on  May 05, 2005

 

 

Hydro electricity Page : Punatsangchhu Project  :Chukha Project  :Tala  Project : Kurichhu Project

 

 

BASOCHU HYDRO POWER PROJECT, WANGDUEPHODRANG

 

Basochu Upper Stage Hydropower Project:  The 24 MW (first phase) Basochu Upper Stage Hydropower project will have an annual generation output of 105 Million Units. The power plant is a run-of the river scheme tapping the Basochhu river three kilometers upstream of the waterfall with a catchment area of 162 square kilometre.  The Basochhu stream at 1,800 metres above sea level is tapped and brought to the Rurichhu basin to produce 24MW, called the Upper Stage. The 40 MW Lower Stage uses the tailrace water of the Upper Stage combined with the Rurichhu that has been diverted into a reservoir of 74,000 cubic metres capacity. The water is piped through a 2.5-kilometer tunnel and a 1.3 kilometre long penstock long penstock line before it hits the pelton turbine

 

he project is financed by the Austrian Government under a financing mix of bilateral assistance and soft loan. The construction of the first phase started in November 1997 and was completed in August 2001.

 

Cost: The construction of the project began in 1997. The original project cost  was estimated at Nu. 1,569 million. The government of Austria provided Nu. 1,227 million, partly as grant and partly as an interest-free loan for this project (Kuensel Jan 18,2002). Austria provided a grant of Euro 13.038 million, an interest free loan of Euro 17.151 million (Kuensel May 03, 2005). Bhutan financed infrastructure development, mainly the 66KV transmission line to Semtokha, the roads to Hebesa and the intake area with a total investment of Nu. 342 million. The two countries shared the escalated cost of Nu. 354 million on a 50-50 basis. (Kuensel Jan 18,2002).

 

Generation and Revenue: According to Basochhu Power Corporation, Phase 1 produced 130 million units of energy in 2004 compared to 119 million units in 2003 and 110 million units in 2002, an increase by 23.8 percent. Revenue generation also increased to Nu. 121, up by about Nu.13 million from the previous year (Kuensel May 03, 2005).

 

Basochhu Power Corporation sells its energy to Bhutan Power Corporation ( BPC) at Nu.0.5 a unit The BPC then  supplies power to himphu, Paro, Wangduephodrang, Haa and Punakha.  It also sells its energy to the Chukha Hydro Power Corporation at a tariff of Nu.1.5 a unit, which is fed to the domestic industries in the southern belt. Loss of energy from transmission failure dropped to 512 Mwh (Nu.0.512 million) in 2004 from 1754 Mwh (Nu.1.754 million) in 2003

 

There are 51 employees to operate and maintain both upper stage (24MW) and lower stage (40MW), which came into operation since September 8, 2004.

 

Basochu II Lower Stage (Rurichu) Hydropower Project:  The construction of the lower stage or the phase II of the Basochhu project was started in March 2002. The Austrian minister for Foreign Affairs, Dr. Ursulla Plassnik and Bhutan's prime minister, Lyonpo Yeshey Zimba, jointly  inaugurated the Basochhu Lower Stage hydro power project in Wangduephodrang on March 26 by switching on the generators of the 40 MW project phase, increasing the total power output of Bhutan to 457 MW.

 

With the total production capacity of 40 megawatts, the lower stage is already supplying 32 megawatts of power to the domestic western grid since September 2004. The Basochhu power will be linked with Kurichhu supply at Gelephu to form an integrated national power transmission grid. The project went into commercial operation supplying 32 megawatts of power to the domestic western grid. The Bhutan Power Corporation is buying the power at 0.50 cheltrums a unit from the Basochhu Hydro Power Corporation.  This raises generation from Basochhu to 64 megawatts, with the first phase or Upper Stage already generating 24 megawatts. However, the lower stage is currently generating only 9MW because of the low volume of water in the two streams.  It is expected to generate annual energy generation of 186 Million Units. The  lower stage powerhouse is located 18.0 km from Wangduephodrang.

 

Cost: A turn-key project agreement was signed on September 13, 2001 between the Royal Government of Bhutan and Austrian Hydro Consortium Basochu (AHCB) for the lower stage of the Basochu project. The project is financed under Official Austrian Export Promotion Scheme Loan.  It is being  implemented as a turnkey package - financed with a loan of Nu. 1,300 million   (ATS 430 million) from the Official Austrian Export Package Scheme (OAEPS). Bhutan’s contribution is to the tune of  Nu. 369 million, mainly  for infrastructure development to transmit power to Semtokha. A contract worth Nu 1,300 million (ATS 430 million) to construct the 40 MW Basochu Lower Stage (Basochu II) was awarded to  AHCB in September 2001.  The lower stage is built at a cost of Nu. 1,422 million (2001-2002 pricing) of which 90 percent of the loan is provided by Austria making it the biggest Austrian-Bhutan cooperation project. Cost per MW comes to  Nu 35.55 million.

 

The Lower Stage is a high head plant and lies below the Upper Stage and is designed to utilize water released by the upper stage Basochhu I with additional 20 percent flow tapped from the nearby Rurichhu. An 870 metre long tunnel will convey water from Rurichhu to a reservoir, in front of the upper stage powerhouse, from where it will be taken to the powerhouse downstream through a 2.53 km penstock pipe. It has two ‘pelton’ turbines and is similar in design to the Upper stage.

 

During the winter months when power consumption peaks the country had to buy power from India for a few hours a day with Chukha providing only 70 -80 megawatts. Now this shortfall will be met by the supply from the Basochhu Lower Stage.

 

Basochhu II along with Basochhu I, which is already in operation, will have a total installed capacity of 64 MW. Together they will earn Nu 300.0 million a year. The power from both the projects will be supplied to the five western dzongkhags and will also be extended to Tsirang, Dagana and Sarpang. The ultimate strategy is to link Basochhu power with the Kurichhu supply at Gelephu to form an integrated national power transmission grid.  The Basochu project is the biggest Austrian - Bhutan cooperation project and also the biggest project assistance that Austria has signed with a third country.

 

All the equipment and the power plant of the Lower Stage are from Austria except for the switchyard and the transmission lines which were built by the Bhutan Power Corporation. The  total domestic consumption at around 105 megawatts.  This  project would provide electricity for about 300,000 domestic consumers in Bhutan

 

 

Basochhu Lower Stage Power House