|
6. PROJECTS
All 20 districts in
Bhutan are accessible by road, constructed entirely by Indian Border
Road Organisation. India has funded all major projects in Bhutan,
some of which are as follows:
1. Penden Cement
Plant
2.
Chhukha Hydro
Power Corporation (CHPC)
3. Paro Airport
4. Bhutan
Broadcasting station
5. Bhutan-India
microwave link
6. Exploration,
survey and mapping of mineral resources
7. All major
Highways ( road)
Penden Cement
project
In February 1982,
Bhutan’s first cement plant, Penden Cement Project started it
commercial production. Its installed capacity was
the 300 tons per day.
It was constructed at a cost of NU/IRS 142 million, funded by the
Government of India. The surplus is exported to neighbouring Indian
states.
Chhukha hydroelectricity project (CHEP)
The current online
Chhukha Hydroelectricity Project (CHEP)
was entirely
funded by the Government of India.
India constructed the
336 mega watt
Chhukha Hydroelectricity Project (CHEP) - Bhutan’s first mega
power project on a turnkey basis. The project costing NU/IRS 2,470
million ( then approximately US $ 200 million) was successfully
commissioned in October 1998. India provided a 60 percent grants and
40 percent loan at 5 percent per annum repayable in 15 years in equated
annual instalments, the first repayment commencing 3 years after
each withdrawal of the loan.
The Government of
India at the insistence of Bhutan increased tariff of the Chukha
power on 01 April 1997. The power tariff was revised from 50 paise
to Re 1.00. India further revised the tariff to Rs 1.50 per unit
on July 01, 1999.
The project was handed over to Bhutanese management in June
1991. 70% of power generated by this project is
exported to India. It has an installed capacity of 336 MW.
In 1998,
electricity
valued at
Rs1338.8 million
was exported
to
India.
In 2000, It exported electricity worth
Rs
1650 million
to India.
In
2000, according to the government newspaper Kuensel, the Chhukha
Hydro Power Corporation alone contributed Nu. 2007.3 million ( US $
40.75 million –Eds) to the national exchequer. Today, the power
sector contributes about 45 percent to the gross revenue generation
in the country and accounts for about 11 percent of the GDP.”
Ngultrum is at par with Indian rupees. The Chhukha Hydro
Power Corporation (CHPC) manages the project.
According to the government sources, by
the year 2006, Bhutan would be exporting about 6,400 MUs of power
annually. The revenue from hydropower projects along with earnings
from the other traditional revenue sources could reach about Nu. 15
billion annually.
Paro Airport
The Government of
India provided financial and technical assistance in the
construction (runway and the hangar ) of Bhutan’s first and only
Paro airport in 1990. The Government of India also funded the
Phase II construction ( terminal building, control tower and cargo
warehouse ) of Paro Airport on turnkey basis at a cost Nu/IRS
217.5 million. It was completed in April 1999.
PROJECTS UNDER IMPLEMENTATION
Tala Hydro-electric Project: In the early eighties, the two
new potential hydroelectricity
projects -- 1020 MW Tala Hydroelectric Project (THEP) and 500
MW Chhukha II -- were identified as two downstream hydroelectricity
projects of Chhukha. The 1020 MW THEP was taken up for implantation
in 1996. It is located in Tala, 60 km up from Phuntsholing, the
gateway to Bhutan. The THPC has an installed capacity of 1,020 MW.
It is
a run-of-the-river project on the Wangchu river, downstream of
Chukha Hydroelectric project
. Please visit
Hydro project- Power projects
of Bhutan page for full information on Bhutan's hydro power project
and Indian assistance.
It
will comprise a 92-meters dam, a 22.25 kilometre long head race
tunnel, an underground power house complex at Tala village to house
6 units of 170 MW generators. and three 440 KV single-circuit
transmission lines to reach the Ind0- Bhutan border.
The original cost for the THEP
was estimated at Bhutanese (Ngultrum) Nu 14.80 billion ( Us $ 0.3
billion). The cost of project has been revised at
Nu/Rs
30,000 million (
approximately $ 600 million)
The THPC is the biggest Indo-Bhutan joint project.
This
project is entirely funded by the Government of India (GOI) by way
of grants and loan. India will provide a 60 percent grants and 40
percent loan at 9 percent interest. It will produce 3,962 million
units (MUs) of power in a "90 percent dependable year".
The construction of initial work on the dam, power tunnel, power
house complex and transmission system was started in 1998. It is
targeted for commissioning in the year 2004-2005. Bharat Heavy Electrical
Limited of India is the supplier of the complete generating plant
at a cost of Nu. 4,210 million.
Tala
Hydro-electric Project Authority (THPA)
manages the
project.
M/s
Hindustan Construction Company, M/s Larsen and Toubro and M/S
Jaiprakash Industries
are other Indian contractors.
Kurichhu
hydro-electric Project: The second hydroelectricity project was planned and implemented
in quick succession. The Kurichhu hydro-power project is having
an installed capacity of 60 MW. The project planned to install 45
MW with three 15 MW generators in the first phase and later install
the fourth generator. The project is located in Gyepshing, Mongar
in eastern Bhutan. The project will generate 322 MUs in a "90
percent dependable year".
The
cost of Kurichhu project in the initial agreement was estimated
at Nu. 2,560 million and was revised in 1994 to Nu. 2,860 million.
It was again revised at
Nu.5600
million
( $ 110 million)
The project is also being fully funded by the GOI. The GOI will
provide 60 percent as a grant the and 40 percent as a loan at 10.75
percent interest. The pay-back period will be mutually agreed upon.
The National Hydro-power Corporation of India is the turn-key contractor
of the project. The Kurichhu project is expected o be fully commissioned
by June 2002. The two generating units of the Kurichu hydroelectric
project have been connected to the Indian grid at Salakati, Assam
state of India. The National Hydroelectric Power Corporation (India)
Limited (NHPC) completed the 198 kilometres of 132kv transmission
line from Gyelposhing to Gelegphug via Pema Gatshel, Nganglam, Panbang
and Tingtibi. The Kurichhu power will be available to the districts
of Mongar, Trashigang, Trashiyangtshel, Pema Gatshel, Samdrup Jongkhar,
Gaylegphug and Zhemgnag. The Water and Power Consultancy Services
(India) Limited of India is the consultants to the project.
Dungsum Cement
Plant (DCP)
The Government of
India has agreed to provide Nu/IRS. 4,000 million for the
construction of Dungsam Cement Project (DCP). Out of which, Nu/IRS.
1,000 million is earmarked for infrastructural development. The DCP
is a dry-process plant. It is envisaged to produce 500,000 tons per
year. The project is a joint venture between ACC Ltd., India and the
Royal Government of Bhutan. Initially, the ACC, India held 20%
equity with the balance 80% equity remaining with the Royal
Government of Bhutan. However, due to security reasons, ACC has
withdrawn from the DCP. The DCP has been facing problems due to the
insurgency problems in the north-east India.
FUTURE
PROJECTS
Sunkosh:
On January 4, 1993, Bhutan and
India in signed a MoU for the preparation of the DPR for the Sankosh
Multi-purpose Project. The Sunkosh Multipurpose Project (SMP) is the
biggest identified hydroelectricity project of Bhutan. The Central
Water Commission of India (CWC) was retained as the contractor to
prepare a Detailed Project Report (DPR) on the project. Accordingly,
after three years’ study, the CWC submitted a 37 volume DPR on the
SMP, to the Royal Government of Bhutan (RGOB) on December 30, 1997.
The SMP could be
Bhutan’s largest hydroelectricity project. According to the DPR, it
would have two power stations with an installed capacity of 4,060 MW
of power. The cost is estimated at Nu 77.93 billion ( Us $ 1.60
billion). The cost could escalate in ten years. The SMP will be
located at Karbari village in Sarbhang district in Southern Bhutan.
The project would comprise two dams, the main one for power
generation and the second to feed a 141 kilometres irrigation canal.
Out of the proposed 141 kilometres canal, only 13 kilometres of
canal will be inside Bhutan while the rest will be in India. It
would supply power to the entire North-east and reach as far as
Merrut in Uttar Pradesh state of India. It would irrigate and supply
drinking water to the Indian states of West Bengal and Bihar. The
project is expected to take about 10 years to complete.
Bhutan has
already submitted two project reports on the development of 360 MW
Mangdechhu and the 870 MW Puna Tsangchhu hydroelectric projects to
the Government of India. It has requested the Government of India to
consider financing of these two hydroelectricity projects along the
Kurichhu and Tala modalities. The Mangdechhu power project is
estimated to cost about US$ 349 million, whereas the Puna Tsangchhu
will cost around US$ 813 million.
|