|
|
CONTENTS
-
Kurichhy Hydroelectric Project Authority (KHEP)
-
Project
Details
-
Current News on the KHEP
-
Dam photo
KURICHHU
HYDRO-ELECTRIC PROJECT
The second hydroelectricity project was planned and implemented
in quick succession. The 60 MW run-of-the-river Kurichhu hydro-power project
on Kurichhu river is located in Mongar district of eastern Bhutan. The project planned to install 45
MW with three 15 MW generators in the first phase and later install
the fourth generator. The project is located in Gyepshing, Mongar
in eastern Bhutan.
The
cost of Kurichhu project in the initial agreement was estimated
at Nu. 2,560 million. It was revised in 1994 to Nu. 2,860 million.
It was again revised at
Nu.5600
million
( $ 119 million)
The project is also being fully funded by the GOI. The GOI will
provide 60 percent as a grant the and 40 percent as a loan at 10.75
percent interest. The pay-back period will be mutually agreed upon.
The National Hydro-power Corporation of India is the turn-key contractor
of the project. The Kurichhu project is expected o be fully commissioned
by the end of 2002. The two generating units of the Kurichu hydroelectric
project have been connected to the Indian grid at Salakati, Assam
state of India. The National Hydroelectric Power Corporation (India)
Limited (NHPC) completed the 198 kilometres of 132kv transmission
line from Gyelposhing to Gelegphug via Pema Gatshel, Nganglam, Panbang
and Tingtibi. The Kurichhu power will be available to the districts
of Mongar, Trashigang, Trashiyangtshel, Pema Gatshel, Samdrup Jongkhar,
Gaylegphug and Zhemgnag. The Water and Power Consultancy Services
(India) Limited of India is the consultants to the project.
During the period between April 2003
to March 2004, a total of 256.80 MUs of power was exported to
India
2. Project details
Total Energy Output: 400 MUs on
the basis of 90% dependable flow.
Cost on completion :
Nu.5600
million
Generation Tariff : Nu. 1.75
per unit
Source: Kurichhu River in
eastern Bhutan
Net Head: 33 m
Capacity : 4 x 15 MW
Date of Commissioning : 3 units
of 15 MW each were commissioned on 3 November 2001 and
the fourth was commissioned in 2002
Beneficiaries: India's West
Bengal State Electricity Board (WBSEB) and Damodar Valley
Corporation (DVC) .
|
|
|
|
3. NEWS ON THE PROJECT
Cleaning up the
Kurichhu project
Kuensel July 17, 2004
Restoration and cleaning work at the Kurichhu Hydropower Project was
“in full swing”, according to the director of the Department of
Energy, Sonam Tshering. Sonam Tshering told Kuensel that 60 to
70 employees of the Bhutan Power Corporation have begun re-building
the 27th transmission tower, three hours walk from Kurichhu
downstream, after it was completely destroyed by the flood. The
flood washed away the whole foundation of the tower. “The new
transmission tower is expected to be completed in three weeks at the
earliest,” Sonam Tshering said. Cleaning operations were also in
full progress to remove the silt and logs clogging the tailrace
tunnel. The clogging was caused by the breaching of the Tsatichhu
lake, about 35 kilometres from the Kurichhu Project, at about 4.20
pm on Saturday, July 10. The first waves of the flood reached the
Kurichhu dam at about 6.30 pm. The furious flood, with tonnes of
logs and debris, had passed through the dam by 8.00 pm. According to
the Kurichhu officials all the deposited silt and logs will have to
be flushed out to restart generation. With the Kurichhu project
shut down and the Indian grid not available Mongar, Lhuentse,
Trashigang and Trashiyangtse are expected to be without power from
Kurichhu project for at least three to four weeks. Meanwhile, the
1.1 MW Rangjung power plant, which was reinstated on July 13, was
shut down at 6.00 am yesterday since the intake area was full of
boulders. The plant, however, will start generation today.
Trashigang town is expected to get electricity through the Rangjung
line. The intake at the Chenary micro plant which started generation
last October was completely washed away. So has been the Khaling
power house which was flooded on July 10. Kurichhu has been
incurring a daily revenue loss of Nu. 2.5 million since it shut down
on July 10.
--------------------------
Tsatichhu lake bursts, Kurichhu shut down
Kuensel July 11, 2004
Gyalpoishing,
Mongar: 11 July 2004 - The Tsatichhu lake, about 35
kilometres from the Kurichu Hydropower Project, burst (breached) at
about 4.20 pm on Saturday, July 10, cutting off power supply from
the project and causing other damages downstream. The first
waves of the flood reached the Kurichhu dam at about 6.30 pm but, by
then, advance warning from a flood warning unit in Ladrong village,
opposite Tsatichhu lake, had enabled the Kurichhu project officials
to lower the reservoir level to withstand the onslaught of the
flood. The furious flood with tonnes of logs and debris, had passed
through the dam by 8.00 pm. While the project authorities are
in the process of assessing flood related damages and its effect on
the project they have reported that the dam and power house were not
damaged by the flood. "At first hand, mostly scouring is evident in
the reservoir area and downstream of the power house and these will
not affect the operation of the project," said the managing director
of Bhutan Power Corporation (BPC), Chhewang Rinzin. "However a lot
of silt and logs have been deposited in the tailrace area of the
power house and all this would have to be flushed out to restart
generation." The flushing is expected to take some time,
depending on the flow in the Kurichhu river. The flood washed
away a transmission tower about 15 kilometres downstream of the
Kurichhu project. Other adjacent towers were also bent. Without the
towers and the line, the Kurichhu project is now desynchronized from
the Indian grid. "BPC is mobilizing its resources to put the line
back into operation at the earliest," said the managing director.
"But, with the need to construct new towers, it will be a formidable
task because all tower/line and construction material will have to
be head-loaded." He said that this was further complicated because
nearly all the roads in eastern Bhutan were blocked after incessant
rain over the past week. It took a minimum of three weeks to
construct a new tower and restore the line even under normal
conditions. With the Kurichhu project shut down and the Indian grid
not available Mongar, Lhuntshi, Trashigang and Trashi Yangsti are
expected to be without power from Kurichhu project for at least
three to four weeks. Meanwhile BPC's Khaling power house was flooded
on July 10 and BPC had to temporarily evacuate its staff from the
colony. The intakes of both the Rangjung and Chenari power houses in
Trashigang have also been washed away. BPC has also lost a number of
its distribution network systems because of landslides in the
region. The mini hydropower plants in Lhuntshi and Mongar are
working but, if the rain continues, the scenario could change any
day, Chhewang Rinzin told Kuensel. To add to BPC's woes a
number of towers between Pema Gatshel and Deothang had already
collapsed after heavy rains last week, cutting off Kurichhu power to
Deothang and Samdrup Jongkhar. Efforts to restore the line were
being seriously hampered by the continuing rain. BPC has not been
able to arrange an alternate power supply from Rangia, India, for
Samdrup Jongkhar and Deothang because, according to the Assam State
Electricity Board, a number of poles have collapsed between Rangia
and Samdrup Jongkhar and ASEB was not able to restore the line
because of rain and floods in Assam. "BPC requests all to bear
with the inconveniences," the managing director announced. "We are
mobilizing all our resources in all parts of the country to deal
with the situation."
|
|