KURICHHU HYDRO-ELECTRIC PROJECT

 

Updated on April 06,  2005

 

 

Hydro electricity Page : Basochhu Project :Chukha Project  :Tala  Project : Punatsangchhu Project

 

 

CONTENTS

 

  1. Kurichhy Hydroelectric Project Authority (KHEP)

  2. Project Details

  3. Current News on the  KHEP

  4. Dam photo

 

KURICHHU HYDRO-ELECTRIC PROJECT

 

The second hydroelectricity project was planned and implemented in quick succession. The  60 MW run-of-the-river Kurichhu hydro-power project on Kurichhu river is located in Mongar district of eastern Bhutan.  The project planned to install 45 MW with three 15 MW generators in the first phase and later install the fourth generator. The project is located in Gyepshing, Mongar in eastern Bhutan.

 

The cost of Kurichhu project in the initial agreement was estimated at Nu. 2,560 million. It was revised in 1994 to Nu. 2,860 million. It was again revised at Nu.5600 million ( $ 119 million)

 

The project is also being fully funded by the GOI. The GOI will provide 60 percent as a grant the and 40 percent as a loan at 10.75 percent interest. The pay-back period will be mutually agreed upon. The National Hydro-power Corporation of India is the turn-key contractor of the project. The Kurichhu project is expected o be fully commissioned by the end of 2002. The two generating units of the Kurichu hydroelectric project have been connected to the Indian grid at Salakati, Assam state of India. The National Hydroelectric Power Corporation (India) Limited (NHPC) completed the 198 kilometres of 132kv transmission line from Gyelposhing to Gelegphug via Pema Gatshel, Nganglam, Panbang and Tingtibi. The Kurichhu power will be available to the districts of Mongar, Trashigang, Trashiyangtshel, Pema Gatshel, Samdrup Jongkhar, Gaylegphug and Zhemgnag. The Water and Power Consultancy Services (India) Limited of India is the consultants to the project.

 

During the period between April 2003 to March 2004,  a total of 256.80 MUs  of power was exported to India

 

2. Project details

 

Total Energy Output: 400 MUs on the basis of 90% dependable flow.

Cost on completion : Nu.5600 million

Generation Tariff : Nu. 1.75 per unit

Source: Kurichhu River in eastern Bhutan

Net Head: 33 m

Capacity : 4 x 15 MW

Date of Commissioning : 3 units of 15 MW each were commissioned  on  3 November 2001 and the fourth was commissioned in  2002

Beneficiaries:  India's West Bengal State Electricity Board (WBSEB) and Damodar Valley Corporation (DVC) .

 

 

 

3. NEWS ON THE PROJECT

Cleaning up the Kurichhu project

Kuensel July 17, 2004

 

Restoration and cleaning work at the Kurichhu Hydropower Project was “in full swing”, according to the director of the Department of Energy, Sonam Tshering.  Sonam Tshering told Kuensel that 60 to 70 employees of the Bhutan Power Corporation have begun re-building the 27th transmission tower, three hours walk from Kurichhu downstream, after it was completely destroyed by the flood. The flood washed away the whole foundation of the tower. “The new transmission tower is expected to be completed in three weeks at the earliest,” Sonam Tshering said.  Cleaning operations were also in full progress to remove the silt and logs clogging the tailrace tunnel. The clogging was caused by the breaching of the Tsatichhu lake, about 35 kilometres from the Kurichhu Project, at about 4.20 pm on Saturday, July 10. The first waves of the flood reached the Kurichhu dam at about 6.30 pm. The furious flood, with tonnes of logs and debris, had passed through the dam by 8.00 pm. According to the Kurichhu officials all the deposited silt and logs will have to be flushed out to restart generation.  With the Kurichhu project shut down and the Indian grid not available Mongar, Lhuentse, Trashigang and Trashiyangtse are expected to be without power from Kurichhu project for at least three to four weeks.  Meanwhile, the 1.1 MW Rangjung power plant, which was reinstated on July 13, was shut down at 6.00 am yesterday since the intake area was full of boulders. The plant, however, will start generation today. Trashigang town is expected to get electricity through the Rangjung line. The intake at the Chenary micro plant which started generation last October was completely washed away. So has been the Khaling power house which was flooded on July 10.  Kurichhu has been incurring a daily revenue loss of Nu. 2.5 million since it shut down on July 10.

 

--------------------------

 

Tsatichhu lake bursts, Kurichhu shut down

Kuensel July 11, 2004

 

Gyalpoishing, Mongar: 11 July 2004 - The Tsatichhu lake, about 35 kilometres from the Kurichu Hydropower Project, burst (breached) at about 4.20 pm on Saturday, July 10, cutting off power supply from the project and causing other damages downstream.  The first waves of the flood reached the Kurichhu dam at about 6.30 pm but, by then, advance warning from a flood warning unit in Ladrong village, opposite Tsatichhu lake, had enabled the Kurichhu project officials to lower the reservoir level to withstand the onslaught of the flood. The furious flood with tonnes of logs and debris, had passed through the dam by 8.00 pm.  While the project authorities are in the process of assessing flood related damages and its effect on the project they have reported that the dam and power house were not damaged by the flood. "At first hand, mostly scouring is evident in the reservoir area and downstream of the power house and these will not affect the operation of the project," said the managing director of Bhutan Power Corporation (BPC), Chhewang Rinzin. "However a lot of silt and logs have been deposited in the tailrace area of the power house and all this would have to be flushed out to restart generation."  The flushing is expected to take some time, depending on the flow in the Kurichhu river.  The flood washed away a transmission tower about 15 kilometres downstream of the Kurichhu project. Other adjacent towers were also bent. Without the towers and the line, the Kurichhu project is now desynchronized from the Indian grid. "BPC is mobilizing its resources to put the line back into operation at the earliest," said the managing director. "But, with the need to construct new towers, it will be a formidable task because all tower/line and construction material will have to be head-loaded." He said that this was further complicated because nearly all the roads in eastern Bhutan were blocked after incessant rain over the past week. It took a minimum of three weeks to construct a new tower and restore the line even under normal conditions. With the Kurichhu project shut down and the Indian grid not available Mongar, Lhuntshi, Trashigang and Trashi Yangsti are expected to be without power from Kurichhu project for at least three to four weeks. Meanwhile BPC's Khaling power house was flooded on July 10 and BPC had to temporarily evacuate its staff from the colony. The intakes of both the Rangjung and Chenari power houses in Trashigang have also been washed away. BPC has also lost a number of its distribution network systems because of landslides in the region.  The mini hydropower plants in Lhuntshi and Mongar are working but, if the rain continues, the scenario could change any day, Chhewang Rinzin told Kuensel.  To add to BPC's woes a number of towers between Pema Gatshel and Deothang had already collapsed after heavy rains last week, cutting off Kurichhu power to Deothang and Samdrup Jongkhar. Efforts to restore the line were being seriously hampered by the continuing rain. BPC has not been able to arrange an alternate power supply from Rangia, India, for Samdrup Jongkhar and Deothang because, according to the Assam State Electricity Board, a number of poles have collapsed between Rangia and Samdrup Jongkhar and ASEB was not able to restore the line because of rain and floods in Assam.  "BPC requests all to bear with the inconveniences," the managing director announced. "We are mobilizing all our resources in all parts of the country to deal with the situation."

 

 

 

 

4. Dam

 

Kurichhu Hydroelectricity Project

 

 

Kurichhu Power Plant