TALA HYDROELECTRIC PROJECT AUTHORITY (THPA)

 

Updated on  April  06, 2005

 

 

Hydro electricity Page : Basochhu Project :Chukha Project  :

Punatsangchhu Project : Kurichhu Project

 

 

CONTENTS

 

  1. Tala Hydroelectric Project Authority (THPA)

  2. Project Details

  3. Tala Update

  4. Current News on the THPA

  5. Dam photo

 

 

1. TALA HYDROELECTRIC PROJECT AUTHORITY (THPA)

 

In the early eighties, the two new potential hydroelectricity projects -- 1020 MW Tala Hydroelectric Project Authority (THPA) and 500 MW Chukha II -- were identified as two downstream hydroelectricity projects of Chukha.  The THPA, a run-of-river scheme immediately downstream of the Chukha project on Wangchu river is envisaged to generate 3,962 Million units of power in an average year. The Ministry of Trade,  Bhutan says is planned to generate 4865 Million Units per year. This project is the largest high-head (860m) power plant being constructed in the region.

 

A run-of-the-river project,  the 1020 MW THPA was taken up for implantation in 1996. It is located in Tala, 60 km up from Phuntsholing, the gateway to Bhutan. The THPA has an installed capacity of 1,020 MW. It is a  run-of-the-river project on the Wangchu river, downstream of Chukha Hydroelectric project.   It comprises  a 92-meters high dam, a 22.25 kilometre long head race tunnel, an underground power house complex at Tala village to house 6 units of 170 MW generators and three 440 KV single-circuit transmission lines to reach  the Ind0- Bhutan border.

 

The 23-kilometre headrace tunnel, second longest in the Himalayas, was completed on November 8, 2004 ( Kuensel Nov 10, 2004). The project’s managing director, Mr. R. N. Khazanchi. said that with excavation works completed,  only concreting was left to be done, the rest of the 23 kilometre long headrace tunnel will be completed by October 2005. ( Kuensel Jan 29, 2005). The excavation of the tunnel took about 20 months, which in normal condition would have taken only about two months.  The excavation was delayed due to adverse geological conditions. The Tala tunnel will be ready for delivering water to the six 170 MW generators by October 2005.

 

The first 4.4 kilometre stretch of  Geduchu headrace tunnel was inaugurated on January 27, 2005

 

The project originally planned to be commissioned in June 2005, will now be commissioned in June 2006. The project is expected to transform the country’s economic health. Estimates suggest that Bhutan’s annual per capita income would increase from about $700 to about $1200.

 

Project Costs: The original cost for the THPA was estimated at Bhutanese (Ngultrum) Nu or Indian Rupees  14,080 million ( Us $ 0.3 billion) in 1993. The cost of project  was then revised at Nu/Rs 30,800 million in 2001,  Nu. 37,250 million ( 37.25 billion or  app. US $ 750 million )  in March  2003 and  Nu. 43,000 million on January 22, 2004. The project  may cost to Nu. 43,450 million, an increase by Nu. 7650 million from the initial estimation, informed the Managing Director of the project on February 14, 2005

 

The THPA is the biggest Indo-Bhutan joint project. This project is entirely funded by the Government of India (GOI) by way of grants and loan. India will provide a 60 percent grants and 40 percent loan at 9 percent interest. It will produce 3,962 million units (MUs) of power in a "90 percent dependable year". The construction of initial work on the dam, power tunnel, power house complex and transmission system was started in 1998. It is targeted for commissioning in the year 2004-2005. Bharat Heavy Electrical Limited of India is the supplier of the complete generating plant at a cost of Nu. 4,210 million. Tala Hydro-electric Project Authority (THPA) manages the project. M/s Hindustan Construction Company, M/s Larsen and Toubro and M/S Jaiprakash Industries are other Indian contractors.

 

2. Project details

 

Total Energy Output: 3962 MUs on the basis of 90 percent dependable flow.

Estimated Cost : Nu. 37250 Million

Generation Tariff : Nu. 1.60 per unit (estimated)

Source: Wangchu River

Gross Head: 860 m

Dam Height:  92 meter  high.

Head race tunnel: 22.25 kilometre long

Capacity : 6 x 170 MW

Commissioning Schedule :  Project originally planned to be commissioned in June 2005, will now be commissioned in June 2006

Beneficiaries:  India’s Eastern Region Constituents

Revenue projection: Expected revenue generation of Nu/IRS 40 million a day after completion

Per capita Income: Annual per capita income is expected to  increase from about $700 to about $1200 after the completion of this project

 

3. Tala Update

 

The Power Grid Corporation of India (PCI) and Tatas have formed a joint venture for transmission of 3,000 mw of power from Bhutan to the States in north India, including Jammu and Kashmir  via Delhi. The Tatas will have 51 percent and the Power Grid Corporation of India (PCI)  49 percent holding in the joint venture. The project will be accomplished in two phases. In the first phase, 1,000 mw of hydel power will be transmitted from Bhutan. Source: Hoovernews  January 01, 2003.

 

On January 16, 2003 The Asian Development Bank (ADB) said that it has approved a rupee-denominated loan of 62 million dollars for India's first public-private partnership in power transmission.  The joint venture company, Tala-Delhi Transmission Ltd. will construct power transmission lines from Siliguri in West Bengal to Mandaula near New Delhi, according to the ADB  statement. The power lines will carry electricity from the Tala Hydro Electric Power Project  as well as surplus power from India's eastern region to the northern areas.

 

The Tala-Delhi Transmission Ltd. will construct  more than 1,150 kilometers  (713 miles) comprising  1,133  kilometers  of 400 kilovolts (kV) lines and 20 km of 220 kV lines  of power lines under the "build-own-operate-transfer" ( BOOT) set-up.   The total cost of the project is US$249 million equivalent. Debt will make up 70 percent of the financing, with 25 percent from ADB and 45 percent from commercial lenders. The equity financing, covering the other 30 percent of the cost, is divided between Tata Power Company Limited, India's largest private power utility company (49 percent); Tata Sons Limited, the principal investment holding company of the Tata Group (2 percent); and Power Grid Corporation of India Limited (49 percent).

 

The Tala-Delhi Transmission Ltd., will handle the operation of the system for 30 years and then turn it over to the Power Grid Corporation  of India Ltd., a government-owned transmission utility. Sources: Asian Development Bank January 16, 2003.and  Hoovernews  January 17, 2003.

 

 

4. NEWS ON THPA

 

 

Tala will be commissioned in March 2006

Kuensel July 03, 2004
 

The 1020 MW Tala Hydroelectric Project will be commissioned in March, 2006, six months behind its initial date, according to a report released during the 19th Tala Hydroelectric Project Authority meeting in Thimphu on June 26. Allowing one month for filling and another month for testing and trial runs, the first unit will be commissioned by December, 2005, and all the six units by March, 2006, the report states.  According to the report the new commissioning schedule took into consideration the work on the headrace tunnel in the critical reach between Kalikhola and Mirchingchu, excavating and concreting of surge shaft and pressure shafts in the middle reach scheduled for completion in October 2005. Meanwhile, most of the electrical works are expected to be completed by early next year and the construction of two 400kV transmission lines to Indo-Bhutan border was progressing including erection of towers and stringing of transmission lines. Infrastructure like roads and bridges to access the project, the civil, electrical, transmission, and the hydro-mechanical works, were either completed, or was nearing completion.  The civil works, diversion tunnel, dam excavation, intake excavation, headrace tunnel excavation, desilting chambers were completed while dam concreting and intake concreting among others were yet to be completed. In the past one year, the project has been able to overcome some of the critical hurdles created by weak geo-physical condition and monsoon damages said the managing director of Tala Hydroelectric project Authority, Mr. R N Khazanchi. “Despite the initial hindrances, the works are now picking the pace,” he said.

At the Authority meeting, the chairman of the committee, Lyonpo Yeshey Zimba, said there was much concern about the possible delays in project implementation during the last meeting held in Delhi, India, last year.

 

----

 

Tala will be delayed

Kuensel Apr 10, 2004

 

Adverse geological conditions in drilling the headrace tunnel and ‘numerous blockages’ in vertical and inclined pressure shafts might delay the completion of the 1,020 MW Tala hydro electric project by a few months, according to THPA officials.   “We expect the compressed commission date of September 2005 to slip further by a few months,” THPA’s managing director, Mr R N Khazanchi, told Kuensel on April 6.  Mr Khazanchi said that, although 80 percent of the project was completed, about 159 metres of tunneling was still to be completed.   The 42-kilometre tunnel from Mirchingchu to Kalikhola faced difficult conditions between the 23-kilometre area from Wangkha to Kalikhola in a 600- metre stretch.  The vertical and inclined pressure shafts that would filter water flowing through the tunnel also had ‘numerous blockages’ with the latest blockage cleared on March 29.  The coming monsoon rains were also expected to slow the work. “We lose at least a day or two in a month,” said Mr Khazanchi, although all the work in progress was underground except at the dam site. Meanwhile work on the transmission phase of the project, which involves setting up transmission lines for export of power to India from Tala, is in full swing. Power from Tala will reach the Indian border through two main 400 Kv double circuit lines. The 46.67-kilometre Tala-Pugli line is expected to be completed by the end of this year. “Out of a total of 105 towers 87 have already been erected and the foundation laid for 12 more towers,” said Mr B K Sood, the superintending engineer of transmission circle of the project. “Conductors have been strung for 27 kilometres out of 49 kilometers for the Tala-Pugli line,” he added.  The initial complication for the passage of a corridor along the 24.54- kilometer Tala- Khokla line through the Buxa tiger reserve forest in West Bengal was resolved with the existing transmission line of the Chukha power project to be used with slight modifications in height and multi lines.  “This line will be a complete standby line to the Tala-Pugli line,” Khazanchi said.  The transmission line across the Indian border to Siliguri was being constructed by the power grid of India, a government of India undertaking, and the work for the 1,500-kilometre transmission line further to Delhi was started, in collaboration with Tata Power, Khazanchi said. The fabrication and manufacturing of the generating plants was also on track, with most of the equipment already transported to the project site, he added. Once commissioned, THPA is expected to generate a total revenue of Nu 40 million a day and contribute a substantial part to the Ninth Plan budget. As of today, Nu 27,000 million has already been spent, out of the expected completion cost of Nu 40,000 million

 

5. Dam photo

 

Tala -Wankha Dam